Nordic-Baltic Hydrogen Corridor in Krimulda: Zone Widths, Project Numbers and the Questions That Will Shape Latvia's Hydrogen Rules
Krimulda drew the fullest room of the Nordic-Baltic Hydrogen Corridor consultation in Latvia, with 65 people in the hall and 34 online. We go through what Conexus disclosed there, from protective zone widths to the price of the Latvian section, and why the questions asked in Ragana are the ones the whole hydrogen ecosystem needs answered.
NEWS
HydrogenLatvia
11/19/20264 min read


Ragana, 13 August, six in the evening. Sixty-five people sat in the Krimulda community hall and another thirty-four joined on Zoom, which made it the biggest of the ten rooms the Nordic-Baltic Hydrogen Corridor consultation visited in Latvia. No surprise there. The gas transmission line already runs through here, Inčukalns underground storage is next door, and the people who came have lived alongside both for decades. They know what a pipeline corridor does to a property, so their questions were pointed, and the answers they got were more concrete than in any other hall that August. This is the second article in our series on the consultation. The first covered the process; this one covers what was said.
The zone question, answered in metres
Most of the evening went on one question: how wide will the zone be, and what can’t I do inside it? Someone had seen a figure of 219 metres in a document on the project website. Conexus’s Edgars Smiltāns said that was an early calculation based on US standards. Run the numbers to Latvian national standards and local conditions and the width comes out substantially smaller, about 100 metres on the current estimate for a hydrogen pipeline safety zone. The existing natural gas line already carries a 150-metre safety zone. The new pipe would be laid 15 metres from the old one, so its zone would fall inside one that’s already on the land. No widening, in practice.
Two other numbers cleared up a lot of confusion. The operational zone, where nothing may grow, is 15 metres, and it would extend by 15 metres for the new pipe. The 300-metre green band on the map, the one that triggered the letters to landowners, is an information zone and carries no protective status. The building authority has no legal basis to restrict construction on it. If a landowner starts building before the design is finished, it’s the developer who adapts the route. Anyone with a building plot near the corridor should remember that one.
The panel added a caveat of its own. Latvia’s Protective Zone Law has no hydrogen-specific provisions yet and the regulation is still being drafted, so these figures are estimates. The calculated ones will be in the EIA report.
Numbers Conexus put on the table
Krimulda got more hard data than most halls. The pipe is 1,200 mm in diameter with a working pressure of 75 bar. The Latvian section will cost roughly €1 billion, with no state budget money planned; the financing is EU structural funds, Conexus’s own investment and loans. There will be one pipeline. People worried about a second one later were told plainly that any new main pipeline needs a new EIA and a new public consultation. There’ll be no hydrogen storage at Inčukalns, and the route goes around the storage territory. Where the compressor station goes hasn’t been decided and isn’t part of this EIA. It gets its own procedure, with information expected around 2028.
On timing, the panel said public consultation on the report would come no earlier than the second half of 2027, with the EIA possibly running to early 2028 and meetings repeated in every municipality. Smiltāns put the start of construction at around 2030 and commissioning at 2035. The project partners have used 2029 and 2033 in public material, so his dates are later. We wouldn’t read much into the gap while feasibility work is still running.
What the gas line taught this valley
A good share of the evening was memory, and hydrogen barely came into it. Noise in Ragana from the storage facility is already above the 45 dB limit at the facade. Drainage was damaged during repairs on the gas line and never put right. A high-voltage line was built through one property with no compensation, because it fell inside the gas zone. Litter and quad-bike ruts were left on the corridor after works. One participant asked for agro-chemical soil tests before any digging, so there’s a baseline to restore to.
You could hear all that as grievance. The panel treated it as a free audit of what a corridor operator has to get right next time, and we think that’s the better reading. Conexus said land is returned to its pre-works condition and asked people with specific unresolved cases to send their cadastral numbers. The soil-test idea and the cumulative noise and odour assessment with Inčukalns were both recorded for the VVD, and the programme that came out in October does require cumulative impacts to be assessed. A local observation became a line in the scope, which is what a consultation is for.
Property rights and the compensation gap
Can a landowner say no? The panel answered straight. The law requires agreement with landowners, but if the project is granted national-interest status it can proceed in the state interest, with compensation. How that compensation gets calculated was the open question of the night. The Energy Law provides for it when a protective zone restricts a property. What doesn’t exist yet is the Cabinet methodology for calculating it for hydrogen pipelines. One resident asked whether owners could get a share of the project’s economic benefit instead of a one-off payment. Nobody could promise that. Nobody dismissed it either, and it went into the record.
Some things stay as they are. Farming is allowed in the gas line’s zones today and the same approach is expected for hydrogen. A sauna rebuild or a pond inside the existing gas zone follows the rules already in force. Boreholes and their 300-metre zones belong to the storage facility, not to this pipeline.
Why Krimulda was the useful room
It would be easy to file this evening under opposition. We think that’s wrong. The people in Ragana asked the questions the whole Latvian hydrogen sector needs answered before the report consultation in 2027: what the hydrogen protective zone will be in law, how compensation is calculated, who checks the corridor after the contractors leave. Those aren’t objections to a pipeline. They’re the terms on which a pipeline gets accepted. The zone regulation and the compensation methodology are now visibly on the government’s desk because rooms like this one asked for them. Next in the series: Bauska, where the pipe meets Lithuania.
Source: Valsts vides dienests – sākotnējās apspriešanas pārskats